Solicitation No.
|
Type
|
Close Dated
|
Project Name
|
Status
|
Update
|
Details
|
Q-10-001-MR
|
RFQ
|
3/17/10
|
PROFESSIONAL ENGINEERING DESIGN SERVICES - LEON CREEK WATER RECYCLING CENTER (WRC) INTERCONNECT TO THE MEDINA RIVER SEWER OUTFALL (MRSO) PROJECT
|
Selection Approved and Awarded
|
|
[MORE]
|
Q-10-002-MR
|
RFQ
|
3/17/10
|
PROFESSIONAL ENGINEERING SERVICES PRODUCTION AND TREATMENT SCADA MASTER PLAN
|
Selection Approved and Awarded
|
|
[MORE]
|
R-10-001-MR
|
RFP
|
3/11/10
|
2010 AGRICULTURAL LEASES IN UVALDE COUNTY
|
Selection Approved and Awarded
|
|
[MORE]
|
B-10-022-CM
|
IFB
|
3/9/10
|
Traders Village 36-inch Oversize (16-inch Required) Water Main
|
Selection Approved and Awarded
|
|
[MORE]
|
B-10-009-RA
|
IFB
|
3/4/10
|
San Antonio River Improvement Historic Mission Reach, Phase IV
|
Selection Approved and Awarded
|
|
[MORE]
|
B-10-021-CM
|
IFB
|
3/4/10
|
Small Capacity Well Mitigation Program
|
Selection Approved and Awarded
|
|
[MORE]
|
B-10-008-RA
|
IFB
|
3/2/10
|
Terrell Hills Water & Sanitary Sewer Replacement Project Phase II
|
Selection Approved and Awarded
|
|
[MORE]
|
B-10-017-CM
|
IFB
|
2/25/10
|
2010 Water & Sewer Construction Package VIII
(PROJECT CANCELLED)
|
Canceled
|
|
[MORE]
|
B-10-016-CM
|
IFB
|
2/25/10
|
2010 Water & Sewer Construction Package VII
(PROJECT CANCELLED)
|
Canceled
|
|
[MORE]
|
B-10-015-CM
|
IFB
|
2/24/10
|
2010 Water & Sewer Construction Package VI
(PROJECT CANCELLED)
|
Canceled
|
|
[MORE]
|
B-10-014-CM
|
IFB
|
2/24/10
|
2010 Water & Sewer Construction Package V (Project Cancelled)
|
Canceled
|
|
[MORE]
|
B-10-013-CM
|
IFB
|
2/23/10
|
2010 Water & Sewer Construction Package IV
|
Selection Approved and Awarded
|
|
[MORE]
|
B-10-012-CM
|
IFB
|
2/23/10
|
2010 Water & Sewer Construction Package III
|
Selection Approved and Awarded
|
|
[MORE]
|
B-10-011-CM
|
IFB
|
2/19/10
|
2010 Water & Sewer Construction Package II
|
Selection Approved and Awarded
|
|
[MORE]
|
B-10-010-CM
|
IFB
|
2/19/10
|
2010 Water & Sewer Construction Package I
|
Selection Approved and Awarded
|
|
[MORE]
|
R-10-003-DS
|
RFP
|
2/12/10
|
VENDOR TRAINING FOR GROVE 50-TON CRANE OPERATOR CERTIFICATION
|
Selection Approved and Awarded
|
|
[MORE]
|
B-09-078-DG
|
IFB
|
2/10/10
|
Water Production Facility Upgrades Phase III - Mission Pump Station Project.
|
Selection Approved and Awarded
|
|
[MORE]
|
B-10-006-CM
|
IFB
|
2/3/10
|
Large Capacity Well Mitigation Program
|
Selection Approved and Awarded
|
|
[MORE]
|
B-10-005-CM
|
IFB
|
2/3/10
|
Small Capacity Well Mitigation Program ( All Bids Rejected)
|
Closed
|
|
[MORE]
|
B-10-007-RA
|
IFB
|
2/2/10
|
Annual 2010 Pipe Bursting Work Order Construction Contract
|
Selection Approved and Awarded
|
|
[MORE]
|