MEDIO CREEK WRC REHABILITATION PHASE 1

Solicitation No. PS-00160-JP
Status: Selection Pending Negotiation
Due Date: 10:00 AM Wednesday, 11/15/23

REQUEST FOR QUALIFICATIONS (RFQ)

The San Antonio Water System (SAWS) is pursuing Requests for Qualifications for professional engineering services for the Medio Creek WRC Rehabilitation Phase 1 Project (“Project”). Statements of Qualifications (SOQs) from interested firms (Respondents) are being accepted in connection with this Project, which will require the scope of services to be performed by a qualified professional engineering firm.  The selected firm shall provide engineering services entailing planning, engineering evaluations, studies, reports, preliminary engineering, design, bid, construction, start-up/commissioning, and overall project management and coordination services for the design and construction of the Project. 

The anticipated services will include project management and coordination, site/civil, mechanical, structural, and electrical engineering services, instrumentation and controls, surveying, geotechnical investigations, subsurface utility engineering, permitting, preliminary engineering, design, scheduling, cost estimating, construction management and other services as necessary for the Project.

Estimated Timeline

October 19, 2023, at 10:00 a.m. (CDT) Non-Mandatory Pre-Submittal Conference

October 20, 2023, at 9:00 a.m. (CDT)........ Non-Mandatory Site Visit

November 1, 2023, by 4:00 p.m. (CDT) Receipt of Written Questions Due

November 8, 2023, at 5:00 p.m. (CST)....... Q & A Posted to Website

November 15, 2023, by 10:00 a.m. (CST)................. Proposals Due

Non-Mandatory
Pre-Submittal Meeting

10:00 AM, Thursday Oct. 19, 2023
https://saws.webex.com Audio Connection: (210) 233-2090 Meeting Number (access code): 2494 748 4697 Meeting Password: PS-00160

Notify Me

Receive updates sent straight to your inbox.

Interested Firm List

Firms who have obtained the RFQ proposal.

Downloads

Full RFQ Proposal
Note: You will be prompted to login to access the full proposal document.
Pre-Submittal Presentation
Oct. 19, 2023
Pre-Submittal Sign-In Sheet
Oct. 19, 2023
Addendum 1
Nov. 8, 2023