Silver Mountain Pump Station Upgrades
Awarded: 10/5/22
Awarded Firm:
Kimley-Horn & Associates
See Addendum #1 with Changes to Written Questions Due
REQUEST FOR QUALIFICATIONS
The San Antonio Water System (SAWS) is pursuing a Request for Qualifications (RFQs) for professional engineering services for the Silver Mountain Pump Station Upgrades (“Project”). Statements of Qualifications (SOQs) from interested firms (Respondents) are being accepted in connection with the project, which will require the scope of services to be performed by qualified professional engineering firms (Consultants). The selected professional engineering firm shall provide engineering services entailing engineering evaluations, studies, reports, preliminary engineering, design, bid, construction, and overall project management services for the design and construction of the Project.
The services will include, but not limited to, project management and coordination, civil, structural and electrical engineering services, instrumentation and controls, surveying, permitting, subsurface utility engineering, preliminary engineering and studies, design, scheduling, cost estimating, construction management and other services as necessary for the Project.
Non-Mandatory
Pre-Submittal
Meeting
2:00 PM, Thursday Jun. 23, 2022WEBEX ONLY: https://saws.webex.com Audio Connection: (210) 233-2090 Meeting number (access code): 2484 364 8110 Meeting password: 6v7aXP8PCKJ
Downloads
Full RFQ Proposal
Note: You will be prompted to login to access the full proposal document. |
||
Evaluation Criteria FIllable Forms
Jun. 1, 2022 |
||
Non-Mandatory Pre-Submittal Presentation 6-9-2022
Jun. 9, 2022 |
||
PS-00133 Non-Mandatory Pre Submittal Meeting Sign-In Sheet
Jun. 9, 2022 |
||
Addendum #1
Jun. 14, 2022 |
||
Addendum #2
Jun. 17, 2022 |
||
Non-Mandatory Pre-Submittal Presentation 6-23-2022
Jun. 22, 2022 |
||
Non-Mandatory Pre-Submittal Meeting Sign-In Sheet 6-23-2022
Jun. 23, 2022 |
||
Addendum #3
Jun. 30, 2022 |