C-13 Broadway Corridor Package B Project

Solicitation No.
Status: Upcoming Bid Opportunity
Due Date: 12:00 AM Friday, 5/19/17
Estimated Budget: $17,000,000.00

C-13 Broadway  Corridor Package B Project

 

SAWS construction work for the C_13 Broadway Corridor Project Package B will involve the installation of 36-inch and 42-inch gravity sewer main and the rehabilitation of an existing 60-inch gravity sewer main primarily along North Alamo St. between Josephine and Elm Streets. 

 

The construction methods will include:

·         Open cut approximately 350 linear feet of 24-inch sewer main, 3,700 linear feet of 36-inch sewer main, 1,500 linear feet of 42-inch sewer main, and 84 linear feet of 60-inch sewer main.

·         Tunnel approximately 1,500 linear feet of 36-inch and 42-inch sewer main without casing.

·         Tunnel approximately 400 linear feet of 36-inch and 42-inch sewer main with casing.

·         Rehabilitate by hot water/steam Cured In Place Pipe approximately 7,000 linear feet of existing 60-inch gravity sewer main.

 

Items of Note:

·       Construction duration is 15 months.

·       SAWS anticipates multiple work activities occurring simultaneously.

·       Project is located within Texas Department of Transportation and City   of San Antonio Right of Way.

·      Project is part of the Early Action Program of the EPA Consent Decree due to poor pipe condition.

 

Advertisement Anticipated:                May 19, 2017

Construction Anticipated to Begin:    August 2017

Construction Estimate:                       $17.7 Million

 

Minimum Requirements for Similar Experience:

·      Fiberglass Sewer Pipelines (24-inch or greater) with 7 years or more experience.

·       Microtunneling or open face rotary wheel TBM tunneling (lengths 800 feet or greater) with 7 years or more experience.

·      Water/Steam Cured In Place Pipe (48-inch or greater) with 7 years or more experience.