C-13 Broadway Corridor Package B Project
C-13 Broadway Corridor Package B Project
SAWS construction work for the C_13 Broadway Corridor Project Package B will involve the installation of 36-inch and 42-inch gravity sewer main and the rehabilitation of an existing 60-inch gravity sewer main primarily along North Alamo St. between Josephine and Elm Streets.
The construction methods will include:
· Open cut approximately 350 linear feet of 24-inch sewer main, 3,700 linear feet of 36-inch sewer main, 1,500 linear feet of 42-inch sewer main, and 84 linear feet of 60-inch sewer main.
· Tunnel approximately 1,500 linear feet of 36-inch and 42-inch sewer main without casing.
· Tunnel approximately 400 linear feet of 36-inch and 42-inch sewer main with casing.
· Rehabilitate by hot water/steam Cured In Place Pipe approximately 7,000 linear feet of existing 60-inch gravity sewer main.
Items of Note:
· Construction duration is 15 months.
· SAWS anticipates multiple work activities occurring simultaneously.
· Project is located within Texas Department of Transportation and City of San Antonio Right of Way.
· Project is part of the Early Action Program of the EPA Consent Decree due to poor pipe condition.
Advertisement Anticipated: May 19, 2017
Construction Anticipated to Begin: August 2017
Construction Estimate: $17.7 Million
Minimum Requirements for Similar Experience:
· Fiberglass Sewer Pipelines (24-inch or greater) with 7 years or more experience.
· Microtunneling or open face rotary wheel TBM tunneling (lengths 800 feet or greater) with 7 years or more experience.
· Water/Steam Cured In Place Pipe (48-inch or greater) with 7 years or more experience.