WATER RESOURCES INTEGRATION PROGRAM (WRIP) PHASE 2 PUMP STATIONS IMPROVEMENTS

Solicitation No. PS-00025
Status: Selection Approved and Awarded
Awarded: 12/14/16
Due Date: 2:00 PM Wednesday, 5/18/16
Estimated Budget: $3,600,000.00

Awarded Firm: Tetra Tech, Inc.
Tetra Tech, Inc.

                  DIRECTIONS TO MANDATORY PRE-SUBMITTAL SITE VISITS - SEE TWIN OAKS SITE MAP

 

 

The San Antonio Water System (SAWS) is pursuing professional engineering design services for the Water Resources Integration Program (WRIP) Phase 2, Pump Station Improvement Project and is accepting Proposals to continue SAWS’ efforts to improve the Water Resources Integration Program Pump Stations, which will provide the required pressure to transfer water to the integration points.  It is anticipated that additional terminal (ground) storage will be required at the Old Pearsall Pump Station, which will be part of this design package.  These efforts will require a Scope of Services to be performed by a qualified consultant or consulting firm.  The selected firm will be responsible for designing improvements to the Twin Oaks, Old Pearsall and Anderson Pump Stations, as well as existing SAWS infrastructure upgrades and one (1) ground storage tank.  Associated work will include, but is not limited to:  surveying, subsurface and/or geotechnical investigations, electrical design, hydraulic modeling, and system instrumentation and control design.

 

Potential Respondents are required to attend Mandatory Pre-Submittal Site Visits.

Mandatory
Pre-Submittal Meeting

9:00 AM, Tuesday May. 3, 2016
Twin Oaks ASR Plant, 4588 Hardy Rd., Elmendorf, TX 78112

Notify Me

Receive updates sent straight to your inbox.

Interested Firm List

Firms who have obtained the RFQ proposal.

Downloads

Full RFQ Proposal
Note: You will be prompted to login to access the full proposal document.
Twin Oaks Site Map
Apr. 19, 2016
Addendum 1
Apr. 21, 2016
Mandatory Site Visit Sign Ins
May. 3, 2016
Addendum 2
May. 11, 2016
Question and Answers
May. 9, 2016