2022 Water Main Improvements Project

Solicitation No. PS-00122-SM
Status: Selection Approved and Awarded
Awarded: 5/4/22
Due Date: 2:00 PM Thursday, 12/16/21

Awarded Firm: BGE, Inc
Weston Solutions Inc.
Jones & Carter, Inc.
Maestas & Associates, LLC
Bain Medina Bain, Inc.

 The San Antonio Water System (SAWS) is pursuing Requests for Qualifications (RFQ) for professional engineering services for the 2022 Water Main Improvements Project (“Project”). Statements of Qualifications (SOQs) from interested firms (Respondents) are being accepted in connection with this Project, which will require the scope of services to be performed by a qualified professional engineering firm. The selected professional engineering firm shall provide engineering services entailing planning, engineering evaluations, studies, reports, preliminary engineering, design, bid, construction, start-up/commissioning, and overall project management services for the design and construction of the Project.

The anticipated services will include project management and coordination, civil, mechanical, structural, and electrical engineering services, instrumentation and controls, surveying, permitting, geotechnical engineering, subsurface utility engineering, environmental services, archeological services, preliminary engineering, design, scheduling, cost estimating, construction management and other services as necessary for the Project.

SAWS anticipates awarding a contract to more than one Consultant as a result of this RFQ. Contracts awarded may be for a specific identified project basis as outlined in Attachment I - Project Charters and Maps.

Non-Mandatory
Pre-Submittal Meeting

1:00 PM, Tuesday Nov. 30, 2021
WebEx

Notify Me

Receive updates sent straight to your inbox.

Interested Firm List

Firms who have obtained the RFQ proposal.

Downloads

Full RFQ Proposal
Note: You will be prompted to login to access the full proposal document.
Evaluation Criteria Forms
Nov. 16, 2021
Non-Mandatory Pre-Submittal Presentation
Nov. 29, 2021
Non-Mandatory Pre-Submittal Meeting Sign-In Sheet
Nov. 30, 2021
Addendum 1
Dec. 8, 2021