New Sulphur Springs Lift Station and Force Main
Awarded: 4/10/23
Awarded Firm:
Keystone Construction
REQUEST FOR COMPETITIVE SEALED PROPOSALS (RFCSP)
Solicitation No. CO-00635
Sealed proposals are requested by the San Antonio Water System for the construction of a new lift station and force main system along New Sulphur Springs in Bexar County for the New Sulphur Springs Lift Station and Force Main Project, SAWS Job No. 22-1509.
To view additional project information, as well as obtain the plans and specifications for this project, visit our website located at www.saws.org and click on the Business Center. Then select Respondent, Consultant, and Vendor Registration, which is located on the left-hand side of the screen. Select the Register Now button and proceed with registration.
For difficulties downloading plans and specifications, contact the Contracting Department at 210-233-3341.
A non-mandatory pre-proposal WebEx meeting will be held at 2:00 PM (CST) on February 2, 2023, via Webex.
LINK: https://saws.webex.com
Audio Connection: (210) 233-2090
Meeting Number: 2499 435 0379
Password: 635SulphurLS
For questions regarding this solicitation, technical questions or additional information, please contact Janie M. Powell, Contract Administrator, in writing via email to: Janie.Powell@saws.org or by fax to (210) 233-5351 until 4:00 PM (CST) on February 6, 2023. Answers to the questions will be posted to the web site by 5:00 PM (CST) on February 10, 2023 as a separate document or included as part of an addendum. Please be advised that firms responding to this RFCSP (Respondents) are prohibited from communicating with any other SAWS staff, the Consultant, the Developer, or COSA officials regarding this RFCSP up until the contract is awarded as outlined in the Instructions to Respondents.
Due to the COVID-19 emergency and to protect the health of the public, SAWS is implementing new procedures for the submission of proposals. Proposals will be received electronically only, until 3:00 PM (CST), February 21, 20, 2023. Electronic proposals will be received via the secure SAWS FTP site. See the Electronic Proposal Opening Instructions attachment for additional information regarding an electronic proposal submittal. Electronic proposals shall be accompanied by a bid bond in an amount not less than five percent of the total proposal price. (Or, if providing SAWS with a cashier's check or certified check in an amount not less than five percent of the total proposal price, SAWS will request this within 24 hours from the Respondent who did not submit a bid bond). Proposals will then be publicly opened and read aloud by Contract Administration via WebEx.
LINK: https://saws.webex.com
Audio Connection: (210) 233-2090
Meeting Number: 2493 158 1522
Password: 635SulphurLS
Respondents will need to submit a request by February 20, 17, 2023 at 3:00 PM (CST) to receive access to the File Transfer Protocol (FTP) site via email to Janie.Powell@saws.org. Respondent’s email requesting access to the FTP site shall provide the legal name of Respondent’s company and the intended recipient’s email address and phone number. No requests for FTP site access will be accepted after February 20, 17, 2023 at 3:00 PM (CST).
Non-Mandatory
Pre-Submittal
Meeting
2:00 PM, Thursday Feb. 2, 2023https://saws.webex.com Audio Connection: (210) 233-2090 Mtg # 2499 435 0379 Mtg PW 635SulphurLS
Downloads
Evaluation Criteria Forms - Editable Word Version
Feb. 1, 2023 |
||
Pre-Proposal Slides
Feb. 2, 2023 |
||
Pre-Proposal Sign-In Sheet
Feb. 2, 2023 |
||
Evaluation Matrix
Apr. 4, 2023 |
||
Addendum 1
Jan. 23, 2023 |
||
Addendum 2
Jan. 31, 2023 |
||
Addendum 3
Feb. 14, 2023 |
||
Addendum 4
Feb. 15, 2023 |
||
Specifications
Jan. 20, 2023 Note: You must be logged in to access this document. |
||
Plans
Jan. 20, 2023 Note: You must be logged in to access this document. |
||
Bid Tab
Apr. 4, 2023 |
||
Geotechnical Engineering Report - Miro Meadows - LS and Pavement Design
Jan 20, 2023 Note: You will be prompted to login to access this document. |
||
Geotechnical Data Report - New Sulphur Springs Sewer Line
Jan 20, 2023 Note: You will be prompted to login to access this document. |
||
Geotechnical Report Memo - Lift Station